Megan Broome/The Clayton Tribune. Crews continue work on construction of the 750,000 gallon ground-level water storage tank located on Yorkhouse Road in Rabun Gap. It is scheduled to be completed and on line in late September-early October 2023, with a 90-day function testing period to follow.
Construction of the 750,000 gallon ground-level water storage tank located on Yorkhouse Road in Rabun Gap continues as crews completed the pre-stressed wire and structural concrete on the exterior…